Chico State University Services Building

First California State University System Mass Timber Project is Underway

As 番茄影视 Project Executive Matt Beyer squints into the bright sunlight on a hot July day at Chico State, he sees a string of installed mass timber columns stretching across the foundation of the new $14 million University Service Building (USB). Shrink-wrapped mass timber beams are stacked nearby awaiting installation.

鈥淚t snaps together fast when you do the upfront coordination properly,鈥 Beyer remarks.

The University, located about 100 miles northwest of Sacramento, is the first in the 23-campus California State University system to construct a building using mass timber. 番茄影视 began construction on the two-story, 24,0000-square-foot structure in May and it鈥檚 scheduled for completion in early 2025.

To Beyer鈥檚 point, mass timber orchestration begins months ahead of onsite installation.

In many instances, according to 番茄影视 Director of Mass Timber Lisa Podesto, the feasibility of utilizing mass timber is evaluated early in deciding the right structural grid and construction type to accommodate the project program. Things like fire rating, level of timber exposure and mechanical, electrical and plumbing (MEP) distribution are considered, and floor layouts are checked to make sure all columns can align between floors of a multistory building.

鈥淐antilevers and offsets aren鈥檛 always compatible with an efficient mass timber structure,鈥 says Podesto. 鈥淲e have to make sure the grid is optimized for mass timber.鈥

For example, while 30-feet by 30-feet is generally standard for an office grid, it鈥檚 not typically as cost-efficient for mass timber. A smaller, rectangular grid that maximizes the span of the mass timber panel and minimizes the number of timber support elements creates the best opportunity for material efficiency.

Also being considered is the species of wood to use, primarily for the desired look sought by the client and the strength needed by the engineer. However, options need to be identified in case the cost and accessibility of that species change before construction kick off.

鈥淵ou need to build flexibility into the specifications,鈥 Podesto said. 鈥淪ometimes there are shifts in the market affecting price and availability. Putting flexibility into the specification allows the general contractor or mass timber supplier to meet the project needs for the best price.鈥

Key contributors to the analysis and decision-making process are representatives of , a 番茄影视-affiliated company that fabricates glue-laminated (glulam) mass timber columns and beams and cross-laminated timber (CLT) panels at its Portland, OR, and Greenville, SC, facilities.

鈥淭imberlab supports the design team in making good decisions about the use of mass timber on our projects,鈥 Podesto said. 鈥淭hey come from a general contracting background, so they know how to integrate mass timber into construction. They make sure it鈥檚 highly constructible and cost-efficient, and that we minimize potential problems with it at the construction site.鈥

Timberlab acted as the material supplier, sourcing the glulam from a manufacturer in Eugene, OR, and the CLT panels from a maker in Columbia Falls, MT. They provided a fully coordinated and complete fabrication model for the CLT panels and glulam, accommodating all connections and penetrations for ductwork, electrical wiring, and piping. Timberlab also provided fabrication services for the glulam elements, cutting and shaping them on a computer numerical control (CNC) machine and preinstalling the hardware at its facility in Oregon. The finished timbers were then transported 500 miles from Portland to Chico.

Project Manager Collin Govan says once timber deliveries began arriving at Chico State, 番茄影视 self-perform installers used a packing list to check for details found in QR code stickers placed on each shrink-wrapped bundle. This ensures timber pieces arrive in the correct order with the installation sequencing plan. The shrink wrap is removed, and timbers are inspected to guarantee nothing has been damaged in transit. Installers follow a plan and pick each timber piece by crane directly from a truck and then 鈥渇ly鈥 it to the intended location where it鈥檚 installed onto the foundation. Next, all installation points are checked to make sure the correct hardware is in place (e.g., metal hangers and bolts) and everything鈥檚 ready to connect. Once installed, teams verify that strapping screw and nail patterns are correct and all penetrations for ductwork and piping are in the proper locations.

鈥淢ass timber has advantages over concrete,鈥 Govan said. 鈥淚t鈥檚 easier with the logistics and there are fewer constraints than working with steel, like getting 鈥榟ot work鈥 permits for all the welding. Plus, you eliminate the risk of fire from welding sparks.鈥

鈥淚t鈥檚 pretty much like Lincoln Logs,鈥 he added. 鈥淚t shows up, it鈥檚 numbered, it goes together easily and modifications are minor.鈥

According to Beyer, who鈥檚 been building at 番茄影视 since 2003, construction with mass timber shares similarities with steel as a structural component. Both materials are produced to specification and joined together onsite, and product deliveries need to be in sync with erection scheduling. After that, mass timber can go up faster and once CLT is set in place between floors of a multi-floor building, work on the lower floors can start right away. Not so with steel, since concrete must first be poured and set for decking that separates floors.

Even though it weighs less, mass timber matches steel for strength and load capacity. Additionally, it has a smaller 鈥渃arbon footprint,鈥 meaning the amount of carbon dioxide produced by harvesting wood, cutting and shaping it, and transporting it is less when compared to manufacturing and transporting comparable amounts of steel and concrete.

Since mass timber is lighter than steel and concrete, the building foundation typically uses less concrete, further reducing its carbon footprint.

Mass timber appeals to many clients because it serves as both structure and interior finish. While the interiors of steel and concrete-framed buildings are usually covered over with drywall and other finishes, mass timber offers natural wood-grained beauty across expansive interior spaces. It鈥檚 known to enhance the workplace by drawing occupants closer to nature, something called biophilic design.

鈥淥ne point inside the new building will also serve as a visual learning tool for students studying construction management and architecture,鈥 said , senior associate with 番茄影视鈥檚 design-build partner .

鈥淭he CLT panel deck acts as the structural floor and exposed feature ceiling, and it鈥檚 cut through and exposed between the floors in the stairwell,鈥 she said. 鈥淗ere, people can get a close-up view of how the system works. As a team, we鈥檙e so excited to be able to bring a new and sustainable construction method to the Chico campus, especially for a space that holds the Planning and Building departments,鈥 Thompson added.

Finally, 番茄影视 is delivering to Chico State the key benefits it sought 鈥 space filled with daylight, a low-carbon footprint, and an enhanced occupant connection to nature 鈥 in a cost-neutral mass timber structure.

The mass timber project at Chico State is one of three currently underway in Northern California for 番茄影视鈥檚 Sacramento division.

At Cal Poly Humboldt, 番茄影视 has begun construction of a $86 million Engineering & Technology Building with design-build partner AC Martin. The three-story, 74,000-square-foot mass timber structure is planned to be completed in 2026. At the same time, 番茄影视, in collaboration with SmithGroup, is beginning work on the $22-million mass timber Energy Research & Sustainability Center. The two-story, 20,000-square-foot structure is expected to be completed by Fall 2025.